Road works at Wonthella

Published: Wednesday, 30 January 2019 at 2:48:32 PM

The City of Greater Geraldton wishes to advise works will be undertaken on Howard Street to construct additional off street parking bays. In addition, road resurfacing works will begin on Fifth Street between Howard Street and Flores Road commencing on Friday 1 February 2019 for a period of approximately six weeks.

These works are part of $3,965,000 allocated in the 2018/19 Budget for road renewals, which will see approximately 12.5km of the roads resurfaced.

The anticipated hours of work will be from 7am to 6pm and traffic management will be in place during this time. Members of the community are requested to exercise caution and obey all warning signs and directions from authorised City personnel and contractors.

The City apologises for any inconvenience these works may cause.