New footpath construction works in Strathalbyn

Published: Thursday, 16 July 2020 at 8:02:58 AM

The City of Greater Geraldton wishes to advise a new footpath will be constructed in Strathalbyn on the western side of Fallowfield Street between Sunnybanks Drive and Strathalbyn Road.

Works are scheduled to commence the week of Monday 20 July 2020 for a period of approximately four weeks.

The anticipated hours of work will be from 7am to 6pm with traffic management in place during this time.

Members of the community are requested to exercise caution and obey all warning signs and directions from authorised City personnel and contractors.

The City apologises for any inconvenience these works may cause.

If you have any queries please contact the City on (08) 9956 6600 or email council@cgg.wa.gov.au